ASCENT Data Center

Alpharetta, GA
Owner Ascent
Design Assist Mechanical icon Mechanical
Value of icon's Work $6,000,000+

icon was recently awarded the mechanical scope on the expansion of the current, Tier III, 185,000 SF Ascent Data Center in Alpharetta, GA. The expansion will bring the data center to 16 MW.

Our Scope of Work

Mechanical to Include:

–   Equipment for (2) new Mechanical Rooms (Chillers, HX, CTs, Side-Stream Separators, Pumps, Chemical Treatment, etc.)

–   Adding 48 Closed-Coupled Coolers for Additional Data Hall

–   Removing Air Handling Units that Provide HVAC & Pressure Control from the WCC Loop and adding them to the new,              icon-installed ACC Loop (Chillers, Pumps, Glycol System)