Mozel Chemical Process Facility
Owner | Model Chemical, Inc. |
---|---|
Design Build Mechanical | icon Mechanical |
Value of icon's Work | $1,100,000 |
icon Mechanical served as the Design/Build Mechanical Contractor and Commissioning Manager for this $15 million chemical blending facility. The 190,000 square foot facility has many process mixing, blending, batching, and storage areas.
icon Mechanical was responsible for the complete design/build construction effort for the process and utility applications, including managing the process controls and electrical design. We started this project with a verbal specification. The owner was currently closing an existing facility. Their existing facility was a 50-year-old process that was in need of significant improvements. Together with the owner we developed a strategy for getting the existing plant closed and relocating its equipment into the new facility. We designed and implemented a new process that would be more reliable, efficient, safe, and cost effective.
icon’s Design/Build team developed process and instrumentation diagrams (P&ID’s). From these documents we ordered all long lead items (equipment, piping specialties, instrument). Then we detailed and developed our mechanical design, general arrangements, piping layouts and isometrics.
Responsibilities
- Design/Build Contractor
- Utility Systems
- Instrument air systems
- Nitrogen systems
- Hot Water System
DeProcess Systems
- Solvent Storage & Mixing
- Resin Storage & Mixing
- Minor additions Storage & Mixing
- Hazardous Area installations (explosion proof equipment, working in exp. area…)
Commissioning Manager
- Solvent Storage & Mixing
- Resin Storage & Mixing
- Minor additions Storage & Mixing
- Hazardous Area installations
- Instrument air systems
- Nitrogen systems
- Hot Water System