Washington University Campus Renewal Penthouse

Owner BJC Healthcare
Architect HOK
Construction Manager ACW Alliance
Design Build Mechanical icon Mechanical
Value of icon's Work $15,621,519

All systems constructed in the Penthouse starting from design through construction were the responsibility of icon Mechanical. This would include structural, concrete, drywall, electrical, plumbing and mechanical installation.

All the major systems would be fabricated in modules months before needed. A total of 8 pumps skids weighing as much as 30,000 lbs each were shop fabricated as well as over 20 pipe racks and modules weighing in some cases over 30,000 lbs and 70’ long. All of the chillers, boilers, pumps and pipe racks would be set in place in a couple weeks so that only final connections to equipment would be necessary. Total time to construct the Penthouse and have chilled water online was 6 months. This method would be the only way to construct this Penthouse in that time period.

Project Highlights

Turn Key Mechanical Penthouse – 34,000 sq. ft.

Prefabricated mechanical systems consisting of over 700 feet of 24” welded piping.

Winter free cooling heat exchanger

18 pulse VFD driven equipment

7 pump skids

HVAC Systems

Chillers – Trane Centrifugal, four combined 5200 tons

Cooling Tower – Marley, six combined 5200 tons

Boilers – Fulton condensing dual fuel boilers, Six Combined for 36000 MBH

Steam driven humidification

Custom AHU’s – Ventrol, four AHU’s consisting of 34 sections

Planning