icon's role
Fabrication & Modular

icon Mechanical manufactured a fully modular Technology Cooling System (TCS) for a confidential high compute center in the Southeast. Leveraging fabrication capabilities across icon's Granite City, Nashville, and Charlotte shops, the team produced eight TCS loop pipe modules with final assembly completed in Charlotte, North Carolina.

The Phase 1 scope was completed on an aggressive six-week fabrication schedule, with field installation and connection of all modules finished in just five days.

Scope of Work
  • Eight TCS loops, each with three to seven pipe modules
  • Serving 208 rack locations
  • Flexible hose connections to equipment following module installation
  • Flow control valves pre-wired to single control panel by Eagle Controls
Project Insights
  • 13,000 shop hours across three fabrication facilities
  • Six-week fabrication schedule to meet install date
  • Field installation and connection completed in five days