icon Mechanical served as the General Contractor as well as the Mechanical Contractor for this Ameren-Sioux Power Plant in Mid-Eastern Missouri. This outage project consisted of relocating (2) Acid/Caustic Polisher systems, design and fabrication of support systems and piping fabrication, 347 S.S. piping fabrication and installation, demolition and relocation of electrical panels, concrete containment pad (36” high, 3’ thick footer), and hoisting/setting pre-manufactured double walled Bulk Acid/Caustic tanks.
icon Mechanical worked closely with the owner to assist in the successful coordination of the (2) 36 hr. outages for the relocation of the Acid/Caustic polisher heat exchangers, pumps, and piping demolition and tie-ins.
Project Insights
- General Contracting Role
- Site Safety
- AWS-CWI Certification
- 12-hr. shifts
- Uncommon S.S. Material procurement
- Quality Control Plan Design
- Quality Control Plan Implementation
- PTFE lined C.S. piping with Ductle Iron Flanges