ALSTOM Karn Unit 1 Gland Steam/Turbine Retrofit Bay City, MI

Owner
Consumers Energy
Value
$1,727,000
Construction Manager
ALSTOM Power
Architect
ALSTOM Power
Industries
Industrial
Power
Utility
icon's role
Fabrication & Modular
Mechanical Construction
HVAC & Sheet Metal

icon Mechanical leveraged extensive pre-job planning and shop fabrication to deliver the Karn Unit 1 Gland Steam/Turbine Retrofit with the highest quality and customer satisfaction. By shifting fabrication off the critical path of the outage—most notably pre-building the new gland steam valve station on a shipping frame—icon reduced field labor, controlled cost, and protected the owner's schedule during a time-critical turbine outage.

Scope of Work
  • Pre-outage installation of gland steam pipe fabrication in tight areas around the low-pressure turbine condensers.
  • Selective demolition of antiquated gland steam system.
  • Pre-fabrication of new gland steam valve station consisting of approximately 160 welds for high pressure steam. The station was fabricated on a shipping frame, so the installation was completed with 6 tie-in welds reducing cost for the owner and valuable time during the outage.
  • Installation of a new gland steam condenser.
  • Installation of new access ways in the existing condensers walls for access to LP extraction lines and gland steam supply and return pipe work.
  • Installation of new stainless steel hood spray piping on the LPs.
  • Removal and replacement of 16” extraction bellows in the LP condensers.
  • Installation of welded spools on LP extraction lines for reconnection of the lower turbine casings to existing plant piping.
  • Modifications to existing 2” thick turbine gland steam pedestals for installation of new gland steam supply and return piping.
Project Insights
  • ~160-weld valve station prefabbed on a shipping frame → 6 field tie-in welds
  • Built to ASME B31.1 with complete weld mapping + NDE
  • 100% 16 ga. stainless cladding on condenser piping

Tell Us About Your Project

Let's Get Started