NASHVILLE YARDS – TOWER 1 & GARAGE Nashville, TN

Owner
Southwest Value Partners
Value
$8,624,000
Construction Manager
Clark/Bell, A Joint Venture
Architect
Gresham-Smith
Industries
Commercial
icon's role
Design-Assist
Engineering
Fabrication & Modular
Mechanical Construction
HVAC & Sheet Metal

As the design-assist partner engineer, icon Mechanical  delivered the mechanical scope on the core and shell of this 20-story, 566,000 SF Class A office tower—Amazon's Operations Center of Excellence—and its adjacent 600,000 SF parking garage in downtown Nashville, TN.

icon prefabricated to the maximum extent possible, the key to keeping this fast-track project on pace. Working a parallel construction path, icon's installation team set equipment and components on the night shift while the building was still being erected, compressing the schedule by building up and out at the same time.

Scope of Work

Mechanical — Delivery & Install

  • (20) Daikin vertical self-contained units
  • (2) cooling towers, with sand filter
  • Parking garage exhaust system

icon Prefabrication (Granite City, IL — HQ Shop)

  • VAVs pre-assembled with discharge duct and control sensors before transport
  • Pipe and duct risers modularized in-shop, then set by tower crane in 4-story lifts — only two hours of crane time per set
  • 16,000 lb condenser pump skid prefabricated and modularized to the site
Project Insights
  • 20-story / 566,000 SF tower + 600,000 SF parking garage
  • Parallel-path, night-shift installation during structural erection
  • Pipe risers set in 4-story lifts — ~2 hours crane time each
  • 16,000 lb prefabricated condenser pump skid

Tell Us About Your Project

Let's Get Started