Mark Anthony Brewery Columbia, SC

Owner
Mark Anthony Brewing
Value
$40,000,000
Construction Manager
Clayco
Industries
Commercial
Food & Beverage
icon's role
Engineering
Fabrication & Modular
Mechanical Construction
HVAC & Sheet Metal

A surge in demand for White Claw hard seltzer put the owner in immediate need of new capacity, and the answer was a one-million-square-foot, $400 million grass-roots brewery, fast-tracked for a six-month completion in early 2021. The general contractor engaged icon Mechanical for the facility's MEP system design and components, including the central utility plant (CUP).

icon began fabricating CUP components just 15 days after award, then shipped them to the site timed to arrive exactly when needed. icon delivered on schedule, clearing the way for the brewery to open inside its six-month window.

Scope of Work

Central Utility Plant — Chilled Water

  • (4) 950-ton centrifugal, water-cooled chillers and associated cooling towers
  • (3) large pump skids — primary chilled water, secondary chilled water, and condenser water

Steam & Process Hot Water

  • (2) 1,200-BHP steam boilers rated at 41,400 lb/hr
  • (2) 600-BHP steam boilers rated at 20,700 lb/hr
  • (3) 125 GPM / 4,000-gallon steam-fired process hot water heaters
  • Combination deaerator / surge tank

Compressed Air

  • 1,400 CFM, 335-HP oil-free VSD air compressor
  • 1,000 CFM, 250-HP oil-free fixed-speed air compressor
  • Desiccant air dryers delivering a −40°F dew point
Delivering on the Fast Track

Day 1: Project Awarded

Day 15: Equipment released, VDC proceeding, then modularization

Day 90: CUP ready on site

Day 180: Start-up