US Steel – Granite City Works
Mechanical contractor for industrial mechanical work at US Steel's Granite City Works in Southwestern Illinois, completed within nine months with zero injuries on site.
icon Mechanical is proud to have delivered the mechanical systems and components for one of the largest projects in the United States—the $2.64 billion Ultium Cells electric-vehicle battery plant in Spring Hill, TN. This 2.8 million SF joint venture between GM and LG Energy Solution was designed to supply batteries to GM's nearby production plant.
The facility's footprint spans roughly 22 Home Depots, with about 2,000 construction workers on site and 40–60 shipping containers of material arriving daily. Among all bid packages, icon was awarded the largest work scope: a commitment of 69,000 man-hours to the mega-project.
Clean Room Ductwork — Fabrication & Install
HVAC Systems
Logistics & Sequencing
Mechanical contractor for industrial mechanical work at US Steel's Granite City Works in Southwestern Illinois, completed within nine months with zero injuries on site.
Mechanical subcontractor for SunCoke and Gateway Energy's $290 million coke plant serving US Steel, with 120 heat-recovery ovens and steam systems.
Design/build mechanical contractor delivering utility services across a half-million-square-foot Nissan facility, with over 40,000 feet of modularized pipe on 54 racks.
Design/build mechanical for a fast-track office and 200,000-square-foot pharmaceutical production facility built in 82 days, with 27 rooftop units set by helicopter.
Mechanical systems for a 9,600-square-foot data center using a hot-aisle/cold-aisle design, with eight AHUs and four 200-ton air-cooled chillers on variable drives.
icon delivered the mechanical and plumbing scope for this 446,000 SF, 36 MW data center, built for a confidential hyperscale client.